|
Bamboo Installation
Disclaimer:
Requires Vinyl Slip Sheet or concrete sealer for all Nikzad Products.
INSTALLER/OWNER
RESPONSIBILITY
When job site conditions are satisfactory, have the flooring delivered and boxes placed into small lots and stored in the rooms where it will be installed. Bamboo flooring should be acclimate and allow 72 hours or more, for the flooring to become acclimated to job site conditions.
Bamboo
floors are a product of nature and therefore, not perfect.
Our Bamboo floors are manufactured in accordance with
accepted industry standards, which permit a defect tolerance
not to exceed 5%. The defects may be of a manufacturing
or natural type.
·
The installer assumes all responsibility for final inspection
of product quality. This inspection of all flooring
should be done before installation. Carefully examine
flooring for color, finish and quality before installing
it. If material is not acceptable, do not install it
and contact the seller immediately.
·
Prior to installation of any Bamboo flooring product,
the installer must determine that the job-site environment
and the sub-surfaces involved meet or exceed all applicable
standards and recommendations of the construction and
materials industries. These instructions recommend that
the construction and subfloor be dry, stiff and flat.
The manufacturer declines any responsibility for job
failure resulting from or associated with sub-surface
or job-site environment deficiencies.
·
Prior to installation, the installer/owner has final
inspection responsibility as to grade, manufacture and
factory finish. The installer must use reasonable selectivity
and hold out or cut off pieces with defects, whatever
the cause.
·
Use of stain, filler or putty stick for defect correction
during installation should be accepted as normal procedure.
·
When flooring is ordered, 5% must be added to the actual
square footage needed for cutting and grading allowance.
·
Should an individual piece be doubtful as to grade,
manufacture or factory finish, the installer should
not use the piece.
·
Use of appropriate products for correcting subfloor
voids should be accepted as a normal industry practice.
TOOLS
& ACCESSORIES NEEDED
WARNING:
Metal wires are embedded in solid oak parquet flooring
and extreme care and caution should be used when cutting
or trimming this flooring to avoid the risk of personal
injury. Do not use circular saws. Approved safety goggles
or glasses should be worn at all times.
| ·
Broom |
·
Band Saw or Saber Saw |
·
Recommended Adhesive & Adhesive Remover |
| ·
Tape Measure |
·
Moisture meter (wood, concrete or both) |
·
Recommended Hardwood Flooring Cleaner |
| ·
Chalk line & chalk |
·
Carpenter Square |
·
Recommended Trowel |
| ·
Hand saw |
·
Hammer |
|
PRE-INSTALLATION
PROCEDURES
Job
Site Inspection
The building should be closed in with all outside doors
and windows in place. All concrete, masonry, framing
members, drywall, paint and other "wet" work
should be thoroughly dry.
·
The wall coverings should be in place and the painting
completed except for the final coat on the base molding.
When possible, delay installation of base molding until
flooring installation is complete.
·
Exterior grading should be complete with surface drainage
directing water away from the building. All gutters
and downspouts should be in place.
·
Solid oak parquet may be installed on or above grade
level only. Do not install in full bathrooms.
·
Basements and crawl spaces must be dry and well ventilated.
·
Crawl space must be a minimum of 24" (600 mm) from
the ground to underside of joists. A ground cover of
6-8 mil black polyethylene film is essential as a vapor
barrier with joints lapped six inches and taped. The
crawl space should have perimeter venting equal to a
minimum of 1.5% of the crawl space square footage. These
vents should be properly located to foster cross ventilation
(see figure #1).
·
Subfloor must be checked for moisture content using
the appropriate testing method.
·
Permanent air conditioning and heating systems should
be in place and operational. The installation site should
have a consistent room temperature of 60-75° F and humidity
of 35-55% for 14 days prior, during and until occupied,
to allow for proper acclimation.
STORAGE
AND HANDLING
Handle
and unload with care. Store in a dry place being sure
to provide at least a four-inch air space under cartons
which are stored upon "on-grade" concrete
floors. Flooring should not be delivered until the building
has been closed in with windows and doors in place and
until cement work, plastering and all other "wet"
work is completed and dry. Concrete should be at least
60 days old. Bamboo flooring should be stored in the
environment in which it is expected to perform. Air
conditioning/heating systems should be in place and
in operation at least 14 days prior, during and after
installation of the flooring. Check adhesive label for
storage limitations.
SUBFLOOR REQUIREMENTS
SUBFLOORS MUST BE:
·
CLEAN - Scrape, broom clean, and smooth. Free of wax,
paint, oil, sealers, adhesives, curing agents and other
debris.
·
LEVEL/FLAT - Within 3/16" in 10' and/or 1/8"
in 6'. Sand high areas or joints, fill low areas (no
more than 1/8" at a time) with a cementitous leveling
compound or milk additive latex patch of 3,000 PSI minimum
compressive strength. Follow the instructions of the
leveling compound manufacturer. Leveling compounds must
be tested for moisture to ensure they are properly cured
and within the manufacturer's specified requirements
for proper installation.
·
STRUCTURALLY SOUND - Nail or screw any loose areas that
squeak. Replace any water-damaged, swollen or delaminated
subflooring or underlayments. Avoid subfloor with excessive
vertical movement unless they have been properly stiffened
prior to the installation of the wood flooring.
·
DRY - Check moisture content of the subfloor with a
reliable moisture meter.
RECOMMENDED
SUBFLOOR SURFACES
·
PREFERRED: ¾" (19 mm) CDX grade plywood¾"
(23/32") OSB PS2 rated underlaymentMINIMUM:
5/8" CDX grade plywood
· Existing solid wood flooring |
·
Concrete slabs
· Acoustic concrete
· Vinyl,resilent tile,cork flooring
· 3/4" chip, waferboard, particleboard
|
·
Ceramic,terrazzo,slate and marble
· Acoustic Cork
· Metal |
CONCRETE
SLABS
Bamboo flooring can be glued directly to concrete.
Do not use a concrete sealer nor install over one. Surface
preparation using mechanical methods such as sanding
or scouring with open coat paper or a titanium disk
is preferred. The concrete must be of high compressive
strength. All concrete subfloors should be tested for
moisture content. Visual checks are not reliable. Acceptable
test methods for subfloor moisture content include:
NOTE: Test several areas, especially near exterior walls
and walls containing plumbing.
·
A 3% Phenolphthalein in Anhydrous alcohol solution.
Chip the concrete at least ¼" deep (do not apply
directly to the concrete surface) and apply several
drops of the solution to the chipped area. If any color
change occurs, further testing is required.
·
Calcium Chloride test. The maximum moisture transfer
must not exceed 3 lbs./1000 square feet with this test.
·
Tramex Concrete Moisture Encounter meter (figure #2).
Moisture readings should not exceed 4.5 on the upper
scale. (Figure #2 shows an unacceptable reading of over
4.5)
A
"DRY" SLAB, AS DEFINED BY THESE TESTS CAN
BE WET AT OTHER TIMES OF THE YEAR. THESE TESTS DO NOT
GUARANTEE A DRY SLAB. ALL CONCRETE SLABS SHOULD HAVE
A MINIMUM OF 6 MIL POLY FILM MOISTURE BARRIER BETWEEN
THE GROUND AND THE CONCRETE.
Moisture Barrier System: If moisture is present, inexpensive
sheet vinyl or "slip-sheet" (PVC) may be installed.
Use a premium grade, alkaline resistant adhesive and
a full spread application system to properly bond the
vinyl to the subfloor. Follow the sheet vinyl manufacturer
instructions for installation procedures. A patch test
may be required as an adhesion test. Install several
small areas (3' x 3') and allow the vinyl to set for
72 hours. Remove the vinyl; if the backing remains attached
to the concrete, the subfloor should be acceptable for
sheet vinyl installation. If you have any questions
regarding installation or the handling of moisture problems,
please contact the distributor/retailer from whom the
goods were purchased.
ACOUSTIC
CONCRETE
Acoustic
concrete normally contains large quantities of gypsum
that may inhibit the adhesive's capability to properly
bond. Acoustic concrete must be primed with the concrete
manufacturer's recommended primer/surface hardener.
WOOD
SUBFLOORS & WOOD STRUCTURAL PANEL SUBFLOORS
Plywood:
Must be APA grade rated sheathing or CDX minimum. Oriented
Strand Board (OSB): Must be PS2 rated installed sealed
side down.
Particleboard:
Must be a minimum 40-LB density, stamped underlayment
grade and ¾" thick.
Make
sure existing floor or subfloor is dry and well nailed
or screwed down every 6" along each joist to avoid
squeaking or popping before the floor is installed.
The wood subfloor must not exceed 13% moisture content.
Measure moisture content of both subfloor and wood flooring
to determine proper moisture content with a reliable
wood moisture meter (figure #3). The difference between
the moisture content of the wood subfloor and the wood
flooring must not exceed 4%.
Optimum performance of Bamboo floor covering products
occurs when there is no horizontal or vertical movement
of the subfloor. The MINIMUM subfloor recommendations
described above are for 16" O/C joist spacing.
The thicker, PREFERRED subfloor recommendations described
above will allow 19.2" joist spacing if the joist
manufacturer's recommended span is not exceeded. Spacing
in excess of 19.2" O/C may not offer optimum results.
Install flooring perpendicular to the floor joists when
possible. Installations should not be made parallel
to the floor joists or on joist spacing that exceeds
19.2" O/C unless the subfloor has been properly
stiffened. Stiffening may require the addition of a
second layer of subflooring material to bring the overall
thickness to at least 1-1/8".
All
underlayment panels should be spaced 1/8" apart
to insure adequate expansion space. This can be achieved
by using a circular saw set at the depth of the underlayment
and cutting around the perimeter of the panel. T&G
panels normally have built in expansion; DO NOT cut
around the perimeter of T&G panels. Do not install
over existing glue-down wood floors. Do not install
over nailed floors that exceed 3-¼" in width. Wide
width floors must be overlaid with plywood. When installing
over existing wood floors parallel with the flooring,
it may be necessary to install an additional ¼"
layer of plywood to stabilize the flooring or install
the wood floor at right angles. Applicable standards
and recommendations of the construction and materials
industries must be met or exceeded.
VINYL
SLIP SHEET
Clean
the surface thoroughly with a good quality household
detergent. If vinyl appears to have a coating of wax
or other maintenance materials, it must be removed with
the appropriate floor stripper. Allow ample drying time.
(Note: Do not sand any resilient products for they may
contain asbestos fibers, which may be harmful.) Do not
install over floors that exceed two layers
DOORWAY
AND WALL PREPARATION
Undercut
door casings. Remove any existing base, shoe mold or
doorway thresholds. These items can be replaced after
installation. All door casings should be notched out
(figure #4) or undercut to avoid difficult scribe cuts.
GENERAL
INFORMATION ON NIKZAD URETHANE ADHESIVE
NOTE:
When installing Bamboo flooring, allow a minimum of
72 hours adhesive curing time before applying seals,
stains and finishes to unfinished flooring. Trowel filling
and fillers are required to reduce the possibility of
panalization caused by the finish "gluing"
the slats together. Test the moisture content of the
wood in accordance with the stain/finish manufacturer's
recommendations. Avoid installing from the surface of
the flooring. If necessary distribute weight using a
kneeler board.
·
Nikzad Urethane Adhesive – 60 - 90 minutes (Always read
container label before proceeding)
Spread sufficient amounts of recommended Nikzad Urethane
adhesive (shown in header on page 2) with the recommended
trowel (figure #5) in an area that can be covered in
60-90 minutes.
·
Hold the trowel at a minimum 45° angle (figure #6) firmly
against the subfloor to obtain a 50-60 sq. ft. per gallon
spread rate.
·
When not in use, keep the adhesive container tightly
closed to prevent thickening. Thickening of the Nikzad
Urethane will cause difficulty in spreading the adhesive.
·
Proper ventilation within the room must be provided.
An electric fan is helpful.
·
The floor should be installed from several cartons at
the same time to ensure good color and shade mixture.
INSTALLING
THE FLOOR
STEP
1: ESTABLISH A STARTING POINT
·
In at least two places 12"-16" from the corner,
measure out and establish a chalk line parallel to and
24½" away from the starting wall opposite the entrance
doorway. THE ½" IS FOR EXPANSION SPACE (figure
#7).
Snap a second chalk line 90° to the first chalk line,
24½" away from the right angle wall (figure #7).
THE ½" IS FOR EXPANSION SPACE. Check accuracy with
builders square.
·
Make any necessary adjustments to allow for crooked
walls before proceeding.
STEP
2: SPREADING THE NIKZAD URETHANE
·
After both chalk lines (at 90° to each other and 24½"
from the wall) have been snapped, start spreading the
adhesive in the 24½" wide area next to the starting
wall.
·
Continue spreading the adhesive along the entire length
of the starting wall. Be careful not to spread adhesive
beyond the 24½" chalk line.
NOTE: Clean adhesive from the surface of the floor frequently
using the recommended adhesive cleaner. Use clean towel,
changed frequently to prevent haze and adhesive residue.
STEP
3: INSTALLING THE BAMBOO FLOORING
·
Immediately lay the Bamboo planks on the newly spread
adhesive. DO NOT lay the Bamboo floor on dry adhesive
(Always lay the Bamboo floor on wet adhesive). If the
adhesive becomes too dry, scrape up the old adhesive
and spread more. Installing on wet adhesive eliminates
rolling the floor with a heavy roller. The working time
for the adhesive is 60-90 minutes. Working time will
vary depending on the job site conditions. IMPORTANT:
Stand or kneel on the subfloor during the installation
to avoid shifting the Bamboo floor.
·
PROPER PLACEMENT OF THE FIRST FLOOR TILE IS THE KEY
TO THE ENTIRE INSTALLATION. Carefully place a 12"
x 12" Bamboo plank at the intersection of the two
chalk lines (figure #8). Do not use the edge of the
tongue for aligning the Bamboo on the chalk lines.
·
Lay the second Bamboo plank ahead of the first Bamboo
plank to fit ½" from the starting wall. Gently
lock in the tongue and groove between the first and
second Bamboo plank (figure #9).
·
Re-check to be sure both floor tiles are properly lined
up with the chalk line. This is to assure a square starting
area (see figure #9).
·
Continue laying the balance of the 12" x 12"
floor tiles along the starting wall area (see figure
#9). Put each Bamboo plank in place and gently push
the floor tiles together to interlock the tongue and
groove. Align each floor tile squarely.
·
Do not push or shove the Bamboo plank too strenuously
as this could cause the first and second Bamboo planks
to move. Simply realign them and proceed with the installation.
·
Avoid hammering or forcing the Bamboo plank together
as this will destroy the built-in expansion spaces and
may destroy the squareness of the Bamboo plank.
·
After laying the Bamboo plank across the first 24½"
starting area, trim the last Bamboo plank as needed
to obtain the proper ½" expansion space next to
the walls. Use a small band or saber saw for final trimming.
Firmly secure each Bamboo Plank when cutting with a
saber saw.
·
During the installation, occasionally remove a piece
of flooring from the subfloor and inspect the back for
proper adhesive transfer. Adequate adhesive transfer
is necessary to ensure sufficient holding strength.
STEP
4: COMPLETING THE INSTALLATION
·
When the starting area has been completed, including
cutting to the wall, proceed to the second laying area.
·
The second laying area is quite simple as you now have
sufficient Bamboo installed to resist floor tile movement.
·
Again, cut the last Bamboo to allow a ½" expansion
space from the end wall.
·
Proceed by laying areas 3,4,5, etc., repeating the installation
procedure of the starting area. Trim out each laying
area before proceeding to the next area.
·
Maintain the ½" expansion space around the perimeter
of the room and around all fixed objects.
·
Avoid pressing heavily or stepping on the recently Bamboo
Floor as this may destroy the ridging of the adhesive
and positioning of Bamboo floor.
·
Allow a minimum of 24 hours drying time before moving
furniture or walking on the newly laid parquet floor.
i NSTALLERS
- ADVISE YOUR CUSTOMER OF THE FOLLOWING
SEASONS:
HEATING AND NON-HEATING
Recognizing that Bamboo floor dimensions will
be slightly affected by varying levels of humidity within
your building, care should be taken to control humidity
levels within the 35-55% range. To protect your investment
and to assure that your floors provide lasting satisfaction,
we have provided our recommendations below.
·
Heating Season (Dry) - A humidifier is recommended to
prevent excessive shrinkage in wood floors due to low
humidity levels. Wood stoves and electric heat tend
to create very dry conditions.
·
Non-Heating Season (Humid, Wet) - Proper humidity levels
can be maintained by use of an air conditioner, dehumidifier,
or by turning on your heating system periodically during
the summer months. Avoid excessive exposure to water
from tracking during periods of inclement weather. Do
not obstruct in any way the expansion joint around the
perimeter of your floor.
ALL
INSTALLATIONS
STEP
5: COMPLETING THE JOB
·
Clean floor with the recommended Bamboo flooring cleaner.
·
Re-install any transition pieces that may be needed,
such as Reducer Strips, T-moldings, or Thresholds. The
products are available pre-finished to blend with your
flooring. (See moldings below)
·
Re-install all base and/or quarter round moldings. Nail
moldings into the wall, not the floor. Inspect the floor,
filling all minor gaps with the appropriate blended
filler.
·
If the floor is to be covered, use a breathable material
such as cardboard. Do not cover with plastic.
·
Leave warranty and floor care information with the owner.
Advise them of the product name and code number of the
flooring they purchased.
·
To prevent surface damage avoid rolling heavy appliances
and furniture on the floor. Use plywood, hardboard or
appliance lifts if necessary.
MOLDINGS
·
Reducer Strip: a teardrop shaped molding. Used around
fireplaces, doorways, as a room divider, or as a transition
between Bamboo and adjacent floor coverings that are
thinner. Fasten down with adhesive or double-faced tape.
·
Threshold: a molding undercut for use against sliding
door tracks, fireplaces, carpet, ceramic tile, or existing
thresholds to allow for expansion space and to provide
a smooth transition in height difference. Fasten to
subfloor with adhesive and/or nails through the heel.
Predrill nail holes to prevent splitting. Always leave
expansion beneath the undercut.
·
Stair Nosing: a molding undercut for use as a stair
landings trim, elevated floor perimeters, and stair
steps. Fasten down firmly with adhesive and nails or
screws. Predrill nail holes to prevent splitting.
·
Quarter Round: a molding used to cover expansion space
next to baseboards, case goods, and stair steps. Predrill
and nail to the vertical surface, not into the floor.
·
Combination Base and Shoe: a molding used when a base
is desired. Used to cover expansion space between the
floor and the wall. Predrill and nail into the wall,
not the floor.
·
T-Molding: a molding used as a transition piece from
one flooring to another or to gain expansion spaces.
Fasten at the heel in the center of the molding. Leave
expansion beneath the undercut on both sides.
|